KEYERA SOUTH GRAND RAPIDS 20” PIPELINE

Client: Keyera

Timeline: May 2018 - July 2018

Project Value: $2.6 Million

Location: Edmonton Kinder Morgan BTT

PROJECT – South Grand Rapids 20” Pipeline

This project consisted of installing ~1700m of 20” piping in an existing pipe rack in  Edmonton. Structural and piping completed to Keyera and Kinder Morgan specifications.

Structural

▪ Design, procurement, and installation of additional pipe rack supports. Procurement and installation of guides, anchors, and Nylatron pads. Coating structural steel.

Piping

▪ Welding, coating, installation and hydrotesting of 1.7km of 20" piping in existing pipe rack.

▪ Total Exposure Hours: 25,181.

▪ Number of Incidents (FA, MA, LTI): 0.

▪ Project finished ahead of schedule adapting to increases and changes to SoW.

▪ Met multiple client/owner requirements with positive solutions on a tight timeline.

▪ Completed work for Keyera, Kinder Morgan Canada, and TransCanada.